Party wall matters: a simple go to guide

By Anderton Gables

09 Oct 2019

party.jpg

Certain works which are likely to affect your neighbours are covered by the Party Wall etc. Act 1996. This legislation provides protection to all parties involved and is intended to enable the works to be undertaken. In the event of non-cooperation from your neighbour or disagreement, party wall surveyors agree how the works should be carried out, including necessary protection measures and rectification of any damage. The purpose of the act is to avoid litigation by dealing with potential problems up front.

You are legally required under the act to serve a formal written notice to your neighbour if you are planning any works that will involve:-

  • affecting an existing party wall/structure (walls/ceilings/floors separating your property from another)
  • building a new wall at/over the boundary line of your site
  • excavating within 6m of existing buildings/structures on surrounding sites

Some works are considered too minor to require the process of notification. Anderton Gables can advise you on which notices are required, which properties need to be notified, and can serve the notices on your behalf.

Your neighbour or 'Adjoining Owner' can either agree to the works as proposed in the notice, or disagree. If they decide to disagree, or do not respond Party Wall Surveyor(s) will become involved and draw up a Party Wall Award which states how the work should be done and the responsibilities of the various parties involved. The adjoining owner can insist on appointing their own surveyor in addition to your surveyor; however, all party wall surveyors must act impartially, in the interest of protecting all stakeholders and enabling the works to be undertaken. Unfortunately, the cost of all party wall surveyors fees usually will be payable by the building owner proposing the work.

In order to ascertain whether any damage to your neighbour’s property has been caused by the execution of the works, a 'Schedule of Condition' is normally prepared by the party wall surveyor(s) prior to the works, which can then be referred to following completion. The building owner undertaking the works will be liable for any damage caused. For this reason and to avoid false claims, even in the event your neighbour agrees to the works and accepts the notice it is strongly advisable to prepare a Schedule of Condition of their property in the areas which may potentially be affected.

Timing

Party wall matters can cause a delay to the project, so this should be considered reasonably early in the design stage. Depending on the notice required you may need to inform your neighbours up to 2 months prior to your proposed start date. If the project is complex it may take some time for the surveyors to come to an agreement, or several awards may be required. The act does provide various mechanisms for non-cooperation including non-communication of adjoining owners and their surveyors, however there are also rights of appeal and referral to a third surveyor if necessary.

Non compliance

If work requiring a notice is undertaken without notification, or in breach of the notice or non-compliance with the agreed party wall award, a court injunction can be obtained to stop the works.

For all your Party Wall related matters and to seek initial advice please contact Vince Rimmer in our Preston Office Tel: – 01772 562800

Vince sits on the North-West committee of the p&t club – the eminent club for Party Wall Surveyors, and is the only member to achieve Fellow status of the Faculty of Party Wall Surveyors, and listed as an expert Third Surveyor.

Enjoyed this? Read more from Anderton Gables

Latest news

1

Lancashire Skills Hub signs up to support Sub36 Awards Michele Lawty Jones

Lancashire Skills Hub signs up to support Sub36 Awards

21 Jul 2026

2

The Great North calls for a new partnership between government and northern leaders Andyburnham

The Great North calls for a new partnership between government and northern leaders

21 Jul 2026

3

Lancashire’s Fhunded programme celebrates over £35m of early-stage investment Rory Southworth Fhunded Project Lead

Lancashire’s Fhunded programme celebrates over £35m of early-stage investment

21 Jul 2026

4

Canada joins next-generation fighter jet programme BAE Systems GCAP

Canada joins next-generation fighter jet programme

21 Jul 2026

5

Prolight celebrating three decades in the spotlight Prolight 30 1

Prolight celebrating three decades in the spotlight

21 Jul 2026

Blackburn College (July-Aug 26)
Background image for hub sign up block

LBV Hub

Leverage Lancashire Business View platforms

Post your news
Post your events
Post your offers
Build your network
Improve your SEO
Gain coverage in the magazine
Sign-up
Events
LBV130 September/October Magazine Networking Event
Jan/Feb Networking Event - Entrance
Networking
17 Sep 2026

LBV130 September/October Magazine Networking Event

The Beehive Blackburn, Shadsworth Business Park, BB1 2QS

08:30 - 10:30

Built Environment Conference 2026
BEC Listing
Networking
24 Sep 2026

Built Environment Conference 2026

EG On The Move, Waterside Head Office, Blackburn, BB1 2FA

08:30 - 13:00

Sub36 Awards 2026
Awards
16 Oct 2026

Sub36 Awards 2026

Park Hall Hotel & Spa , Chorley

18:00 - 00:00

LBV131 November/December Magazine Networking Event
Jan/ Feb Networking Event - Talking
Networking
19 Nov 2026

LBV131 November/December Magazine Networking Event

Lancashire

08:30 - 10:30

Lancashire Business Day 2026
LBD Listing
Networking
27 Nov 2026

Lancashire Business Day 2026

Burnley Football Club, BB10 4BX

12:00 - 17:00

Preston Tech Connection Coworking Day at Society1
PTC coworking day FB 900 Square.png.png
LBV Hub Networking
23 Jul 2026

Preston Tech Connection Coworking Day at Society1

Society1, Coworking Space, Preston, PR1 3LT

10:00 - 12:00

The AI Lab: Marketing Multiplier
LBV Hub Roundtables
31 Jul 2026

The AI Lab: Marketing Multiplier

Door4, Burnley Wharf, Manchester Road, Burnley, BB11 1JG

09:00 - 11:30

Chamber Breakfast Networking – August
Logo.jpg.jpg
LBV Hub Networking
04 Aug 2026

Chamber Breakfast Networking – August

Morecambe Golf Club, Morecambe, LA4 6AJ

08:00 - 10:00

Morecombe Bay Walk
Morecambe-25-web-gallery4.jpg.jpg
LBV Hub Fundraisers
08 Aug 2026

Morecombe Bay Walk

Arnside, Carnforth, LA5 0HD

13:00 - 18:00

The Ultimate Network
Logo.jpg.jpg
LBV Hub Networking
13 Aug 2026

The Ultimate Network

Garner Hotel , Preston, PR5 0UL

16:00 - 18:00

Mind Over Mountain: Brunch at Ivory Tower
mind-over-mountain-complete.jpg.jpg
LBV Hub Fundraisers
11 Sep 2026

Mind Over Mountain: Brunch at Ivory Tower

Ivory Tower, Preston, PR1 2NL

12:30 - 16:30

Advertise with us

Reaching 50,000 members, our print, digital and event platforms offer a fantastic way to raise your business profile and help you grow.

Find out more LBV124 Online Graphic
Subscribe now

Weekly news bulletin