Time is precious

By Lancashire Business View

03 Jan 2017

A recent study of client satisfaction by Glenigan found that only four out of 10 construction projects in 2015 finished on time.

By Mary Cross, head of contract services, Glovers Project Services.

With advancements in technology such as BIM one would expect performance on site to have improved over the years but it is still almost expected that a job will overrun.

As an expert witness in delay claims I see first-hand the ramifications of when a project goes wrong. Claim costs can mount up quickly and the damage to reputation can sometimes be irreversible.

There are several common reasons for projects being delayed:

skimping on upfront consultant fees an unrealistic programme from the outset poor relationships between client, contractor and subcontractors on site ineffective site management a desire to pass all risk to the contractor So how can the team work together to ensure the project is delivered on time? Start with a fully logic linked programme which factors in time risks Keep accurate records of progress and update the programme regularly Communicate potential issues at an early stage so their impact can be mitigated Embrace BIM technology so potential clashes are ironed out before ground is broken These steps might not eradicate delays but they will place you in a much better position to deal with them as they arise and minimise their impact on the programme. It’s in everyone’s interests to get the project finished on time because nowhere is it truer than in construction that time is precious.

Latest news

1

Development partner wanted for £90m Blackpool homes plan Blackpool Seafront

Development partner wanted for £90m Blackpool homes plan

11 Aug 2026

2

CCA’s new transport chief will drive forward £700m investment budget Karen Cassar

CCA’s new transport chief will drive forward £700m investment budget

10 Aug 2026

3

Big Interview with Tim Webber: Values built in childhood Tim Webber

Big Interview with Tim Webber: Values built in childhood

10 Aug 2026

4

Preferred bidder emerges for Blackburn’s £45m regen scheme Star Square Blackburn Town Centre Regeneration

Preferred bidder emerges for Blackburn’s £45m regen scheme

10 Aug 2026

5

Demand grows at UVS following strategic investments Steve Murphy

Demand grows at UVS following strategic investments

10 Aug 2026

Blackburn College (July-Aug 26)
Background image for hub sign up block

LBV Hub

Leverage Lancashire Business View platforms

Post your news
Post your events
Post your offers
Build your network
Improve your SEO
Gain coverage in the magazine
Sign-up
Events
LBV130 September/October Magazine Networking Event
LBV130 Magazine Launch Social720No Text 17 Sep 2026

LBV130 September/October Magazine Networking Event

The Beehive Blackburn, Shadsworth Business Park, BB1 2QS

08:30 - 10:30

Built Environment Conference 2026
BEC26 WW Logo720 24 Sep 2026

Built Environment Conference 2026

EG On The Move, Waterside Head Office, Blackburn, BB1 2FA

08:30 - 13:00

Sub36 Awards 2026
Sub36 WW Logo720 16 Oct 2026

Sub36 Awards 2026

Park Hall Hotel & Spa, Chorley, PR7 5LP

18:30 - 00:30

LBV131 November/December Magazine Networking Event
LBV131 Magazine Launch Social720No Text 19 Nov 2026

LBV131 November/December Magazine Networking Event

Lancashire

08:30 - 10:30

Lancashire Business Day 2026
LBD26 WW Logo720 27 Nov 2026

Lancashire Business Day 2026

Burnley Football Club, BB10 4BX

12:00 - 17:00

The Ultimate Network
Lancaster And Morecambe Logo 13 Aug 2026

The Ultimate Network

Garner Hotel , Preston, PR5 0UL

16:00 - 18:00

Mind Over Mountain: Brunch at Ivory Tower
mind-over-mountain-complete.jpg.jpg 11 Sep 2026

Mind Over Mountain: Brunch at Ivory Tower

Ivory Tower, Preston, PR1 2NL

12:30 - 16:30

Advertise with us

Reaching 50,000 members, our print, digital and event platforms offer a fantastic way to raise your business profile and help you grow.

Find out more LBV129 Online Graphic
Subscribe now

Weekly news bulletin